OSM were appointed by modular manufacturer Boutique Modern to assist in the development of Garage Studios on Shoreham High Street. The development includes 7 studio flats, split between two storeys built over 4 garages.

The flats and walkways were constructed using volumetric modular units manufactured by Boutique Modern at their factory in Newhaven. The garages were built using traditional construction methods by OSM Construction with the volumetric units deployed on top. The modern design the units included cedar cladding, white render, coloured renders and grey windows and doors.

The on site construction period was 12 weeks.

Contracted works include:

  • - Principal contractor, responsible for overall site management and HSE compliance
  • - Principal contractor, responsible for overall site and project management and HSE compliance
  • - Above and below ground storm and foul drainage
  • - Foundations installation
  • - Garage construction
  • - Responsible for the utility installation and connections
  • - Hard and soft landscaping and external works